Change order

A change is put in writing the day it is asked for, priced on both sides, signed by the customer, and only then billed; subcontracts change with it.

  1. Step 1 · Done by:Superintendent

    Confirm a verbal instruction in writing

    An instruction given on site only counts in a dispute if you confirmed it in writing at once and can prove it arrived.

    Open the task →
  2. Step 2 · Done by:Project engineer

    Ask the customer a question in writing (RFI)

    An RFI (request for information) gets a written answer that protects your cost and time.

    Open the task →
  3. Step 3 · Done by:Project manager

    Record a change on site and price both sides

    You see what the customer pays beside what subcontractors get, so nothing is paid that was never charged.

    Open the task →
  4. Step 4 · Done by:Project manager

    Price a change and get the customer's PO

    Contract value, budget and dates change only when the customer's PO (purchase order) is recorded: no PO, no work.

    Open the task →
  5. Step 5 · Done by:Project manager

    Get the customer to sign a change order by link

    The customer's signature is their written OK to the change; no printing or scanning.

    Open the task →
  6. Step 6 · Done by:Contracts / legal

    Put a signed change order into effect without the customer's PO

    Many customers approve by signing; you can bill the extra without waiting for a PO (purchase order) that never comes.

    Only when the customer issues no PO.

    Open the task →
  7. Step 7 · Done by:Subcontract manager

    Change a signed subcontract

    The subcontract value changes only after finance approves and the subcontractor signs.

    Open the task →