Skip to content

Price a change and get the customer's PO

What it is for

Contract value, budget and dates change only when the customer's PO (purchase order) is recorded: no PO, no work.

Steps

  1. Step 1: Press "New change order": what changes and why, the price to the customer, the days and our cost.
  2. Step 2: Press "Submit for approval". Once approved, press "Send to customer to sign".
  3. Step 3: When the customer's PO arrives, press "Record PO and put the change in force" and attach it.

✓ Done when: The change order shows "In force" and the contract value is updated.

Common mistakes

  • The customer confirmed on paper or by e-mail: press "Record confirmation" and upload the signed paper.
  • The PO is refused: its amount must equal the confirmed price.

Last updated:

Try it in the live demo →