Change a signed subcontract

What it is for

The subcontract value changes only after finance approves and the subcontractor signs.

Steps

  1. Step 1: Open the subcontract and press "New subcontract change", or start from an event with "Change a subcontract".
  2. Step 2: Enter the amount, the days and the reason.
  3. Step 3: Press "Send to finance"; finance presses "Approve" or "Return".
  4. Step 4: Press "Record signature and put in force" with the subcontractor's signed paper.

✓ Done when: The change shows "In force", and the value, lines and date are updated.

Common mistakes

  • Extra money is refused: link a customer change order in force, or write why we bear it.
  • A reduction is refused: pick the line it comes off; it cannot go below what is already claimed.

Note: The person who wrote the change cannot approve it.