Ask the customer a question in writing (RFI)
What it is for
An RFI (request for information) gets a written answer that protects your cost and time.
Steps
- Step 1: Press "New RFI": the question, what we propose and the date the answer is needed by.
- Step 2: Under "Drawings this is about", press "Cite this sheet" on the drawing in question.
- Step 3: Press "Send" and enter who it went to; waiting days count from then.
- Step 4: Press "Record the answer" with the written copy; the project manager then presses "Close RFI" with its effect.
✓ Done when: The RFI shows "Closed" with its effect: none, cost, time or both.
Common mistakes
- The answer adds cost or time: name the change order that carries it when you close the RFI.
Note: The customer can also answer on their project page.