Record a change on site and price both sides

What it is for

You see what the customer pays beside what subcontractors get, so nothing is paid that was never charged.

Steps

  1. Step 1: Press "New event" the day it happens: what, where and who said so. Cite the drawing; no price yet.
  2. Step 2: Press "Price it for the customer": this opens a change order tied to the event.
  3. Step 3: Press "Change a subcontract", choose the subcontract and enter what the subcontractor is owed.
  4. Step 4: When everything under the event is settled, the project manager presses "Close".

✓ Done when: The event shows "Closed".

Common mistakes

  • An event nobody priced shows on the Work tracker under the project manager's name: price it.