Procedures
Subcontract: bid, award, pay application, waiver, payment
A work package goes out for sealed bids, the winner signs by link, each pay application comes with its lien waiver, and retainage is released at the end.
Step 1 · Done by:Project manager
Split the work: own crew or sealed-bid subcontract
Each piece of work gets one owner, and its cost lands on the project either way.
Open the task →Step 2 · Done by:Subcontract manager
Add and approve a supplier or subcontractor
You cannot order from, or subcontract to, a company until it is approved with papers in date.
Open the task →Step 3 · Done by:Subcontract manager
Let suppliers and subcontractors send their own quotes, bids and invoices
They type it in and attach their own paper; nothing counts until you accept it.
Open the task →Step 4 · Done by:Subcontract manager
Sign a subcontract and pay its pay applications
A subcontractor is paid only for work the project manager confirmed, less retainage (the part held back until the end).
Open the task →Step 5 · Done by:Subcontract manager
Get the subcontractor to sign by link
No work is paid before both sides sign; a link gets their signature the same day.
Open the task →Step 6 · Done by:Subcontract manager
Change a signed subcontract
The subcontract value changes only after finance approves and the subcontractor signs.
Only when the scope changes.
Open the task →Step 7 · Done by:Controller
Pay approved invoices in a batch
One person builds the batch and a different person releases it, so no money leaves on one person's word.
Open the task →Step 8 · Done by:Controller
Release a subcontractor's retainage
Retainage (pay held back until the job is done) is paid only after they give up all further claims.
Open the task →