Write the daily site report

What it is for

It is your proof later of what happened on site, day by day.

Steps

  1. Step 1: On the project press "Reports", then "Today's report".
  2. Step 2: Fill in weather, people, hours, work done and tomorrow's plan.
  3. Step 3: Add anything in the way under "Problems and blockers", and add photos.
  4. Step 4: Press "Submit"; the project manager then presses "Confirm" or "Return".

✓ Done when: The report shows "Confirmed" and is locked.

Common mistakes

  • No work that day: report it anyway; tick "No work today" and pick the reason.
  • A confirmed report needs a change: press "Add a correction or note".

Note: You can write a report only for today or the past 7 days.