Write and approve the weekly report

What it is for

It sums up the week for management; its figures freeze when it is submitted.

Steps

  1. Step 1: Confirm every daily report of the week first.
  2. Step 2: Under "Reports" open "This week's report".
  3. Step 3: Write the summary, next week's plan and what you need from management.
  4. Step 4: Press "Submit for approval"; the project manager presses "Approve" or "Return".

✓ Done when: The weekly report shows "Approved" and can be printed.

Common mistakes

  • You cannot submit: a daily report of that week is not confirmed yet; confirm it first.