Write and approve the weekly report
What it is for
It sums up the week for management; its figures freeze when it is submitted.
Steps
- Step 1: Confirm every daily report of the week first.
- Step 2: Under "Reports" open "This week's report".
- Step 3: Write the summary, next week's plan and what you need from management.
- Step 4: Press "Submit for approval"; the project manager presses "Approve" or "Return".
✓ Done when: The weekly report shows "Approved" and can be printed.
Common mistakes
- You cannot submit: a daily report of that week is not confirmed yet; confirm it first.