Sign a subcontract and pay its pay applications
What it is for
A subcontractor is paid only for work the project manager confirmed, less retainage (the part held back until the end).
Steps
- Step 1: Start from a work package award, or press "New subcontract" and write why there was no bid.
- Step 2: Fill in dates, terms and the schedule of values, attach the agreement, and press "Submit for approval".
- Step 3: Press "Record their signature"; an executive then presses "I sign for the company".
- Step 4: For each payment, press "Enter a pay application" with their invoice, the lien waiver and each line's progress.
✓ Done when: The pay application shows "Approved for payment".
Common mistakes
- "Enter a pay application" is not there: the subcontract must be signed by both sides first.
- No lien waiver (their paper saying they won't claim the property): the pay application cannot be entered.
Note: The project manager presses "Confirm the work was done", then finance presses "Approve for payment".