Send a formal notice on time and keep the proof

What it is for

A contract gives only a few days to give notice of a delay or claim; miss it and you lose the right.

Steps

  1. Step 1: Open Formal notices. Under "You may need to send a notice", check the days left and press "Draft the notice".
  2. Step 2: Check the deadline against your contract, write the text and press "Ask for approval".
  3. Step 3: Once approved, print it, send it the way the contract says, and record how, the tracking number and the date.
  4. Step 4: When the receipt comes back, record the delivery date and attach the proof.

✓ Done when: The notice is closed, with its delivery date and proof on file.

Common mistakes

  • You cannot approve a notice you wrote: someone other than the writer must approve it.

Note: The days shown are a general default, not checked by a lawyer; your contract's notice clause decides.