Keep a project inside its budget

What it is for

A purchase that does not fit its budget line is stopped when it is sent, not found out later.

Steps

  1. Step 1: Open the project and press "Budget control". Each line shows its budget, committed, waiting and what is left.
  2. Step 2: See "What counts against this budget": orders, subcontracts, rentals, and approved trips, expenses, hours and warranty work.
  3. Step 3: A purchase was refused? Press "Move budget": choose "Take from" and "Give to", and enter the amount and the reason.
  4. Step 4: No line can give? Under "Ask to exceed the budget", enter the amount and why, and press "Ask an executive".

✓ Done when: The line shows the new amount left, and the refused purchase can be sent again.

Common mistakes

  • The move says "Sent to finance": large moves (over $5,000) wait for a second finance person or an executive.
  • You asked to exceed but nothing changed: it counts only once an executive other than you approves.

Note: Labor counts once: employees' approved hours are cost; for a 1099 contractor (self-employed, paid by invoice) only their invoice is cost.