Collect lien waivers from a subcontractor

What it is for

Each payment is backed by a lien waiver (paper saying they won't claim the property for that money).

Steps

  1. Step 1: Before paying, open the subcontract and, under "Lien waivers from the subcontractor", press "Ask for conditional waiver".
  2. Step 2: The subcontractor signs through the e-mail link, or you upload their signed paper.
  3. Step 3: After the money has gone out, press "Ask for unconditional waiver". Tick "Final payment" on the last one.

✓ Done when: Each payment on the subcontract shows its signed waiver.

Common mistakes

  • No "Ask for unconditional waiver" for a payment: it has not gone out yet; it is only for money really paid.

Note: Have your lawyer check the waiver wording for your state.