Collect lien waivers from a subcontractor
What it is for
Each payment is backed by a lien waiver (paper saying they won't claim the property for that money).
Steps
- Step 1: Before paying, open the subcontract and, under "Lien waivers from the subcontractor", press "Ask for conditional waiver".
- Step 2: The subcontractor signs through the e-mail link, or you upload their signed paper.
- Step 3: After the money has gone out, press "Ask for unconditional waiver". Tick "Final payment" on the last one.
✓ Done when: Each payment on the subcontract shows its signed waiver.
Common mistakes
- No "Ask for unconditional waiver" for a payment: it has not gone out yet; it is only for money really paid.
Note: Have your lawyer check the waiver wording for your state.