Bill progress by % complete

What it is for

The monthly progress bill is drafted for you; you say how far each line is, and the advance and retainage (the share held back until the end) are worked out.

Steps

  1. Step 1: After the month ends, open the draft bill from your work tracker.
  2. Step 2: On each line, type the "% to date" or this period's amount; the other fills in.
  3. Step 3: Materials on site but not installed: under "Stored materials", allow the line, enter the amount and press "Add proof".
  4. Step 4: When those materials are installed, bill them as work on the line and take the same amount off the stored line.
  5. Step 5: Choose the tax and press "Send to finance".

✓ Done when: The bill leaves your work tracker and waits for finance to issue it.

Common mistakes

  • A line will not take your number: no line can be billed past its value.
  • "Send to finance" is refused: stored materials need their proof file (delivery ticket or photo) first.